North Kent Wind 1 - Target Construction Schedule


Construction Task

Start

Finish

Access Roads to Turbine Sites  May, 2017  August, 2017
Operations & Maintenance Facility  June, 2017 October, 2017
Turbine Foundations  May, 2017  October, 2017
Substation  May, 2017  October, 2017
Underground Collection System  May, 2017  November, 2017
Turbine Deliveries (average 5 per week)  September, 2017  October, 2017
Turbine Installation  September, 2017  December, 2017
Turbine Commissioning  October, 2017 January, 2018 
Land Restoration  May, 2018  September, 2018